Recent Court Pleadings in the Southern Bankruptcy Case

Attached are two of the most recently filed court pleadings in the Southern bankruptcy.  The memorandum of decision says that Southern must pay PPL the approximately $2.5 million it sought as payment for power PPL delivered under contract before the PPL/Southern contract was vacated.  This was the administrative claim argued in court last session.  Remember, the whole PPL claim is $374,863,708.19.  

 

 

The second attachment (638) is a request for court approval to hire a consultant to value HGS.  Approval was granted.  